STEP 1: OPEN THE PROJECT & ACCESS THE “ACTIVITIES” PAGE. GO TO HELP & SELECT “USER PRODUCTIVITY KIT”

UPK-IMG1
UPK-IMG1

 

STEP2: SELECT THE UPK TOPIC, FOR EXAMPLE “CREATE ADDITIONAL WBS LEVELS”

UPK-IMG2
UPK-IMG2

 

STEP 3: SELECT THE DESIRED UPK MODE, FOR EXAMPLE “TRY IT”

UPK-IMG3
UPK-IMG3

 

STEP 4: PRESS ENTER TO START THE UPK MODE TO CREATE ADDITIONAL WBS LEVELS, ADD A SIBLING WBS & REPOSITION AS A CHILD WBS ELEMENT

UPK-IMG4
UPK-IMG4

 

STEP 5: SELECT THE APPROPRIATE WBS ELEMENT 

UPK-IMG5
UPK-IMG5

 

STEP 6: FOLLOW INSTRUCTION TO RIGHT CLICK TO ADD THE NEW SIBLING WBS ELEMENT

UPK-IMG6
UPK-IMG6

 

STEP 7: ADD INFO IN THE WBS DETAIL TABS

UPK
UPK

 

STEP 8: USE UP & DOWN ARROWS TO SELECT THE CORRECT POSITION FOR THE WBS ELEMENT

primavera upk
primavera upk

 

STEP 8 Part 2: USE INDENT & OUTDENT ARROWS TO SELECT HIERARCHICAL PLACEMENT

learn primavera
learn primavera

 

STEP 9: SAVE

UPK-IMG10
UPK-IMG10

 

 